Case Study: Working Capital Stress Diagnostic for a Government Contractor

Stabilising a government contractor facing an immediate cash shortfall despite Rs 4 crore of verified receivables

By Ashish Chaudhary•2nd October , 2026•4 MIN READ•Rs 7 Crore Annual Turnover / Rs 4 Crore Receivables
Client & Engagement
Government Contractor
Industry Sector
Civil Construction & Infrastructure
Jurisdiction & Geography
India
Practice Leadership
Working Capital & Financial Advisory
Mandate Performance Metrics
Annual TurnoverRs 7 CroreAnnual revenue of the government contractor
Government ReceivablesRs 4 CroreReceivables outstanding from government departments
Default Risk Window11 DaysTime before the immediate cheque-return risk
Engagement Duration14 DaysUrgent working capital diagnostic

Executive Mandate Summary

Northrop Management Private Limited was engaged to conduct a working capital stress diagnostic for a government contractor facing an immediate liquidity constraint despite ₹4 crore of verified government receivables against approximately ₹42 lakh of near-term payment obligations and only ₹6 lakh of immediately available cash. The review identified that the receivables were not converting into cash at the required pace. Government claims were at different stages of measurement, verification, approval and payment, with ₹48 lakh of claims delayed due to incomplete supporting documentation and ₹62 lakh of claims held against unresolved measurement queries.

Key Transaction & Governance Challenges

  • •
    The contractor had Rs 4 crore of receivables from government departments, but only Rs 6 lakh of immediately available cash against Rs 42 lakh of payments due within 30 days.
  • •
    Government claims were at different stages of measurement, verification, approval and payment processing, making the Rs 4 crore receivable balance less immediately usable than the headline figure suggested.
  • •
    Three claims worth Rs 48 lakh were delayed because required measurement sheets, quality certificates and site photographs had not been submitted.
  • •
    Two claims worth Rs 62 lakh were held following measurement queries that had remained unanswered for approximately six weeks.

Northrop Execution Architecture & Methodology

1
Built a 30-day cash map covering available cash, supplier obligations, labour payments, equipment costs and receivables that could potentially be accelerated.
2
Mapped each government receivable to its milestone, measurement, documentation, verification and approval status and assigned specific actions to move delayed claims forward.
3
Built a documented working capital proposal linking the facility requirement to the actual government receivable cycle, verified claim pipeline and projected repayment capacity.

Executive Mandate Overview

The contractor had Rs 4 crore of receivables from government departments.

The business was profitable and had operated successfully for seven years.

Yet the bank had called a review and the contractor was 11 days away from a potential cheque return.

The issue was not that customers were refusing to pay.

The issue was timing.

Government contract payments often depend on completion milestones, measurement, verification, documentation and departmental processing. Meanwhile, contractors must continue paying suppliers, labour and equipment costs.

Northrop conducted an urgent 14-day working capital diagnostic to stabilise the immediate cash position, accelerate eligible receivables and restructure the working capital facility around the actual operating cycle.

The 30-Day Cash Gap

The immediate cash position was reconstructed.

Cash Available

Rs 6 lakh

Payments Due Within 30 Days

Rs 42 lakh

This created an immediate funding gap of approximately Rs 36 lakh.

The contractor had approximately Rs 4 crore of outstanding receivables.

However, the full Rs 4 crore could not be treated as immediately collectible cash.

Approximately Rs 1.2 crore had completed verification and was already within the government's payment-processing pipeline, with estimated receipt in approximately 25 to 40 days.

The analysis therefore shifted from:

"How much money is owed?"

to:

"How much money can realistically arrive, and when?"

Mapping the Receivable Pipeline

Each receivable was analysed individually.

The review examined:

  • Milestone completion
  • Measurement status
  • Bill submission
  • Verification status
  • Documentation requirements
  • Departmental queries
  • Approval status
  • Estimated payment timing

The Rs 4 crore balance consisted of 11 individual milestone claims at different stages of the payment process.

This distinction was critical.

A receivable that has completed verification and entered payment processing has a different cash-conversion profile from a claim awaiting documentation or measurement clarification.

Unblocking Stuck Claims

Three claims worth Rs 48 lakh were delayed because required documentation had not been submitted.

The missing documentation included:

  • Measurement sheets
  • Quality certificates
  • Site photographs

The documents were prepared and submitted within four days.

Two additional claims worth Rs 62 lakh were being held because departmental officers had raised measurement queries.

The contractor had not responded to those queries for approximately six weeks.

Northrop prepared the responses and the contractor submitted them within three days.

Together, these actions moved approximately Rs 1.1 crore from "stuck" to "processing" within 10 days.

The intervention demonstrated that the immediate cash problem was partly a receivable-management problem rather than solely a financing problem.

Verifiable Institutional Outcomes & Value Realized

  • Claims worth Rs 1.1 crore were moved from "stuck" to "processing" within 10 days through documentation completion and response to outstanding queries.
  • Accelerated claims resulted in Rs 68 lakh of receipts within the following 30 days.
  • The contractor avoided the anticipated cheque returns during the immediate cash-stress period.
  • The bank approved an enhanced working capital facility of Rs 2.2 crore within 60 days after reviewing the documented receivable pipeline and revised cash-flow model.
A

Ashish Chaudhary

Managing Director•Working Capital Diagnostics, Receivable Acceleration & Financial Advisory
Private Mandate Advisory Desk

Facing a Similar High-Stakes Transaction or Turnaround?

Northrop partners execute buy-side due diligence, fraud forensics, and financial restructuring with strict board confidentiality and unmatched technical rigor across Indian jurisdictions.

Next Documented MandateManagement Consulting

Case Study: Ghost Trainees and Unverified Placements in a Skill Development NGO

A skill development NGO reported that 1,200 youth had been trained and 840 placed in jobs under a programme funded through a ₹1.4 crore CSR contribution. The reported 70% placement rate prompted an independent review of beneficiary records, training delivery, placement claims and programme expenditure. Northrop Management Private Limited conducted a forensic verification covering beneficiary deduplication, attendance records, direct beneficiary calls, employer confirmations, offer letters, salary claims and the underlying financial trail.

View Full Mandate Record